Scott Community College
Belmont Road Entrance Renovation
| Engineering Firm: | Ament Engineers and Architects Inc. |
| Project Start Date: | February 2007 |
| Estimated Project Completion Date: | September 2008 |
| Estimated Project Cost: | $452,000 |
Status:
AMENT Inc. has completed all of the surveying, horizontal and vertical line layout, preliminary design, environmental studies, DOT concept statement and preliminary application submittals, roadway design cross-sections, drainage detail, and lighting detail.
The project is on track for all construction documents to be completed and approved for a March 2007 construction bid letting with contracts awarded at the April EICCD Board of Trustees meeting and construction to begin as soon as possible this spring.
Scott Community College
Highway 67 Second Entrance Project
| Engineering Firm: | Ament Engineers and Architects Inc. |
| Project Start Date: | February 2007 |
| Estimated Project Completion Date: | November 2008 |
| Estimated Project Cost: | $2,240,000 |
Status:
AMENT Inc. has completed all of the surveying, horizontal and vertical line layout, preliminary design, environmental studies, DOT concept statement and preliminary application submittals, roadway design cross-sections, drainage detail, and lighting detail.
The project is on track for all construction documents to be completed and approved for a March 2007 construction bid letting with contracts awarded at the April EICCD Board of Trustees meeting and construction to begin as soon as possible this spring.
© EICCD | 306 West River Drive Davenport, IA 52801 | For Information call: 1-800-462-3255