| Architectural Firm: | Gere-Dismer Architects |
| Project Start Date: | November 2007 |
| Estimated Project Completion Date: |
August 2008 |
| Estimated Project Cost: | $400,000 |
Status:
The project design team at MCC has made the recommendation to the EICCD Board of Trustees that the professional services contract be awarded to Gere-Dismer Architects, with the EICCD Board awarding the contract at the December Board of Trustees meeting.
Gere-Dismer Architects has prepared a contract for approval and signature and are preparing a design development schedule to begin implementation and meetings with MCC design team members for completion of the schematic design phase of the project.
The initial kick-off meeting with Gere-Dismer and MCC design team members was held on Monday January 7, 2008. Work has begun to remove all stored items from the building with demolition to follow.